LIKE FACEBOOK

Tweet Feed

Instagram Feed

  • Had a chance to see STS6 Model Tensioners being made at #hiforce headquarters #tensioners #winshawhydraulictools
  • Structural bolt tightening works were carried out on a 50 metre cycle track bridge in Malaysia using Hi-Force TWP22S pneumatic torque multiplier with respective sockets. A total of 568 bolts were tightened within three days and involved tightening of M24, M27 and M30 bolts to a specific torque. #hiforce #bolttightening #torqueing #torquemultiplier
  • Lifting the rear of Saipem FDS2 pipelayer vessel to carry out repair works #hiforce #cylinders #shiprepair
  • Bolt torqueing works at Bloomberg site in London  #hiforce #torquewrench #bolttightening
  • Introducing BOLTRIGHT PRO - the innovative bolted joint integrity software from Hi-Force. Visit www.hi-force.com for more details. #hiforce #boltingtools #boltrightpro
  • Maintenance works carried out on tidal bridges at Richards Bay Coal Terminal in South Africa  #hiforce  #hydrauliccylinders
  • Synchronous lifting of a road bridge in Scotland  #hiforce #HSPsplitflowpump #PLCcontrolsystem
  • Introducing BOLTRIGHT PRO - the innovative bolted joint integrity software from Hi-Force. Visit www.hi-force.com for more details. #hiforce #boltingtools #boltrightpro
  • Bolt torqueing works at Bloomberg site in London  #hiforce #torquewrench #bolttightening
  • Lifting the rear of a Saipem FDS2 pipelayer vessel to carry out repair works http://ow.ly/4n1FCo  #hiforce #cylinders #shiprepair
  • Structural bolt tightening works were carried out on a 50 metre cycle track bridge in Malaysia using Hi-Force TWP22S pneumatic torque multiplier with respective sockets. A total of 568 bolts were tightened within three days and involved tightening of M24, M27 and M30 bolts to a specific torque. #hiforce #bolttightening #torqueing #torquemultiplier
  • International airport terminal construction at Incheon, South Korea  #hiforce #customisedcylinders #HEPpumps
  • Yüksek debili, kapalı fan soğutmalı ve sessiz çalışma özelliği ile harici ve dahili kullanıma uygun
  • Presle monte edilmiş parçaların, tekerleklerin, dişlilerin, cer dişlilerinin, makaraların vb. gibi birçok parçanın sökülmesi işinde kullanılabilen
  • En zor civatalama işlemlerinin bile doğru ve hızlı bir şekilde yapılmasına imkan veren, bağlantı için kullanılan kare başlık tipi ile hızlı bir şekilde aparat sökme ve takma yapılmasını sağlayan, kompakt, hafif, alüminyum ve 360 derece dönebilen bağlantı noktası ile

Synchronous Lifting of a Road Bridge

Synchronous Lifting of a Road Bridge

Synchronous Lifting of a Road Bridge

Synchronous Lifting of a Road Bridge

Synchronous Lifting of a Road Bridge

Synchronous Lifting of a Road Bridge

Synchronous Lifting of a Road Bridge

Hi-Force HSS cylinders, 8-way split flow pump and centralised PLC system assist with synchronous lifting of new road bridge 

The Fourth Road Bridge Company (FCBC) contacted Speedy Services, Hi-Force’s authorized distributor, for a controlled method of lifting 135 road sections and positioning them, for construction of the new road bridge project. Each section weighed 16 tonnes and had to be lifted 220mm before the cement was added to the top of the road section. Once the concrete had set and successfully passed a stress test, the road section then had to be lowered so the self-propelled modular transporters can move in and take them away.

After several discussions and assessing their requirements, Speedy Services along with Hi-Force offered FCBC the 8-way, single acting split flow pump with a centralized PLC Control System, with the capability to ensure the cylinders would lift simultaneously, regardless of the loading on each cylinder, in a synchronized manner. This was the first 8-way split flow pump with a PLC Control System that Hi-Force had ever manufactured and sold.

8 14.5 tonne HSS single acting multipurpose cylinders were also supplied for the job and Hi-Force also sent an engineer to site to perform the first lifts and offer training on the pump operation to the onsite engineers.